Download your PDF
Earned Value Management Calculator result sheet — free, supported by sponsors. Your download button appears in 20 seconds.
This free download is supported by sponsors — continuing in
20
Your file is generated in your browser when you choose Download — nothing is uploaded. If this calculator returns enough numeric data, the export also includes its best-fit chart alongside the readable table.
WorldCalculate result export
Earned Value Management Calculator — result sheet
Calculate schedule and cost variances, performance indices, and a simple estimate at completion from project values.
Inputs used
Results
Visual chart
Breakdown
Calculation steps
Returned data table
Formula and methodology
Formula: SV=EV−PV; CV=EV−AC; SPI=EV/PV; CPI=EV/AC; EAC=BAC/CPI; ETC=EAC−AC; VAC=BAC−EAC.
Earned-value indicators compare the budgeted value of completed work with planned work and actual cost at one measurement date.
This result follows the calculator's declared inputs, precision, validation boundaries, and model limits.
Input contract
- Planned value PV — currency; minimum 1.0E-6; maximum 1.0E+15
- Earned value EV — currency; minimum 0; maximum 1.0E+15
- Actual cost AC — currency; minimum 1.0E-6; maximum 1.0E+15
- Budget at completion BAC — currency; minimum 1.0E-6; maximum 1.0E+15
Worked example
| Input | Value |
|---|---|
| Planned value PV | 50000 |
| Earned value EV | 45000 |
| Actual cost AC | 48000 |
| Budget at completion BAC | 100000 |
SPI = 0.90; CPI = 0.9375; cost variance = −3,000.
Assumptions and limits
- PV, EV, AC, and BAC use the same currency and measurement boundary.
- EAC uses the simple assumption that current cost efficiency continues.
- The result does not replace a schedule network, risk register, forecast review, or project-control standard.
Calculator note
Source and methodology
Use the official WorldCalculate methodology policy for the source, formula, precision, and boundary standards behind this calculator.
Planning estimate, not financial, medical, legal, or professional advice. © WorldCalculate — reuse with attribution. Built and curated by Hassan ALRowaie.
No saved result was found. Please run the calculation first, then choose Download again.